PNM Energy Replacement Plan

PRC Delays Decision On PNM's Coal-Heavy Plan

May 27, 2015
Rita Daniels

People are going to have to wait to find out whether or not New Mexico’s largest utility will be allowed to continue investing heavily in coal power. Regulators decided to delay their decision on PNM’s power replacement plan Wednesday.

Public Regulation Commission Delays Decision On PNM Plan

May 26, 2015
Brainwise via Flickr

UPDATE 12:00p: New Mexico Regulators Delay Decision On Power Plant - Susan Montoya Bryan, The Associated Press

New Mexico regulators are giving Public Service Co. of New Mexico more time to ink agreements with a mining company, delaying a decision on whether to approve a plan to close part of the San Juan Generating Station.

The Public Regulation Commission voted 4-1 during its meeting Wednesday.

Report: High Profits, High Rates For PNM

May 11, 2015
Rita Daniels

Profits at New Mexico’s largest electric company have skyrocketed in the last few years, according to a new report, and demonstrators are planning to protest outside of PNM’s shareholder meeting Tuesday morning. 

PNM Wants Plan Approval Despite Missed Deadline

May 4, 2015
Will Thomas

New Mexico’s largest utility company promised to have a completed coal-supply agreement for their power plant in place by last Friday but PNM missed its own deadline.

The coal-supply agreement for the San Juan Generating Station in northwestern New Mexico is one of the linchpins for the plant’s future energy production. The utility wants to shut down two units there and replace that power with nuclear, natural gas, some solar and more coal.

KUNM Continuing Coverage: PNM's Power Plan

Apr 16, 2015

Two coal-burning stacks at the San Juan Generating Station will be shuttered in 2017. To replace that coal-generated power, Public Service Company of New Mexico has proposed investing mostly in other coal, natural gas and nuclear energy. The utility, which provides power to half a million customers in New Mexico, says it’s the most cost effective, reliable option. 

Hearing Examiner Rejects PNM's Plan For Coal

Apr 8, 2015
Courtesy San Juan's Citizen Alliance

On Wednesday, a Public Regulation Commission hearing examiner recommended against part of PNM’s energy replacement plan for 132 megawatts of coal-generated electricity.

PNM has been looking for a way to replace the energy that will be lost when two coal burning stacks at the San Juan Generating Station are shut down in 2017.

More Comment Sought On PNM Energy Plan

Mar 19, 2015
Sierra Club

    

The Public Regulation Commission is continuing to seek input on PNM’s energy replacement plan. More than 200 people showed up to a meeting in Albuquerque Wednesday night.

Commissioner Valerie Espinoza took a moment during public testimony to say she had received almost 100 written comments opposing PNM’s plan from her constituents in Taos and Las Vegas.

PRC To Take More Comment On Energy Plan

Mar 17, 2015
Wild Earth Guardians

The Public Regulation Commission held weeks of public hearings earlier this year on PNM’s plan to shut down two coal-fired units at the San Juan Generating Station. But this week people in Albuquerque will have one more chance to weigh in.

PRC Chair Karen Montoya said she received requests from her Albuquerque constituents who want their opinions taken into consideration.

“Things could possibly change a lot,” Montoya said. “Depending on what they [at PNM] bring on, it will effect a change in the mix.”

PNM Lost Partners, Stands By Energy Replacement Plan

Jan 21, 2015
Sierra Club

Two groups have withdrawn their support for PNM’s energy replacement plan but the utility insists their proposal is still the best choice for New Mexico.

PNM proposed adding more coal, nuclear, and natural gas energy and less than 5 percent in solar to make up for the loss when two coal-burning units are shut down at the San Juan Generating Station.